WASH Cluster Incident Report №220, 30/09/2019

GOLMOSKIY SEWAGE PLANT SHELLED AND DEENERGISED

 

Voda Donbasa (VD) informed the WASH Cluster that on the morning of Sunday 29th September 2019 (at 7.05 am), the Waste Water Treatment Plant (WWTP) at
Golmovskiy was surrounding by shelling and de-energized as a result of damage to power lines. The WWTP was re-launched from a back-up power line at 9.35
am the same day. A Window of Silence (WoS) is requested for, Monday, October 30 for electrical workers to repair damaged power lines.
For the moment WWTP continues to operate without any back-up power source, receiving wastewater from 7800 people.

The WASH Cluster is in touch with Voda Donbasa regarding this issue.