Subject/Objective: 

AVSI has striven to build long-lasting TLS that can be improved by the community in a bid to increase value for money and foster local ownership. In the presentation are illustrated and justified the technical solutions that were chosen.

Methodology: 

Filed visits

Key findings: 

Context specific approach: technical solutions and costs vary greatly depending on soil composition, environmental conditions that affect durability, and availability of materials
Invest in human resources: in-house construction engineer is needed
Invest in follow up activities, to review durability at 6 months and one year and learn from it
Provide some top-up resources and demand quality in exchange: $10k should be considered the benchmark for a semi-permanent TLS

Assessment Report: 
Assessment Questionnaire: 
Publicly Available
Assessment Data: 
Publicly Available
Operations(s)/Webspace(s): 
Assessment Date(s): 
28 Mar 2019
Status: 
Report completed
Collection Method(s): 
Observation
Population Type(s): 
Conflict affected population
Cluster(s)/Sector(s): 
Leading/Coordinating Organization(s): 
AVSI Foundation
Location(s): 
Eastern Equatoria
Lakes
Theme(s): 
New Way of Working / Nexus